1

Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.

Correct Answer: A is correct but R is not correct

Make the most of this question

This page focuses on one Construction Management question from Engineering. After checking the answer, return to the topic list to practice more or run a timed set.

Construction Management MCQ: Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer. | Extra Education