Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities ofproject PERT is preferred for planning becauseof

Correct Answer: 1, 2 and 4

Make the most of this question

This page focuses on one Construction Management question from Engineering. After checking the answer, return to the topic list to practice more or run a timed set.

Construction Management MCQ: Consider the following features/factors: 1. Projects are of the non-repetitive type 2. Time required need not be known 3. Time required is known precisely 4. Events have been established for planning 5. Emphasis is given to activities ofproject PERT is preferred for planning becauseof | Extra Education