Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. Of these statements

Correct Answer: 1 and 4 are correct

Make the most of this question

This page focuses on one Construction Management question from Engineering. After checking the answer, return to the topic list to practice more or run a timed set.

Construction Management MCQ: Consider the following statements: In the bar chart planning 1. Interdependence of the operations cannot be portrayed. 2. Progress of work can be measured. 3. Spare time of the activities can be determined. 4. Schedule cannot be updated. Of these statements | Extra Education