1

When the bed level of the canal is higher than the highest flood level (H.F.L.) of the drainage, then the cross drainage work is said to be ?

Correct Answer: aqueduct

Make the most of this question

This page focuses on one Irrigation Engineering question from Engineering. After checking the answer, return to the topic list to practice more or run a timed set.

Irrigation Engineering MCQ: When the bed level of the canal is higher than the highest flood level (H.F.L.) of the drainage, then the cross drainage work is said to be ? | Extra Education