1

A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the begining and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would it be finished?

Correct Answer: 5

Make the most of this question

This page focuses on one Math question from English. After checking the answer, return to the topic list to practice more or run a timed set.

Math MCQ: A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the begining and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind schedule would it be finished? | Extra Education