1

Maximum possible time to complete an activity is ---------.

Correct Answer: Pessimistic time

Make the most of this question

This page focuses on one Entrepreneurship question from Faculty. After checking the answer, return to the topic list to practice more or run a timed set.

Entrepreneurship MCQ: Maximum possible time to complete an activity is ---------. | Extra Education