1

The net cash flows of the project and their present values are as follows Year 1 2 3 4 Net cash flow (Rs) 5100 5100 5100 7100 PVIF @12% 0.893 0.797 0.712 0.636 Present Value (Rs) 4554 4065 3631 4516 The initial investment in the project is Rs12500, What is the NPV of the project?

Correct Answer: 4266

Make the most of this question

This page focuses on one Financial Management question from Faculty. After checking the answer, return to the topic list to practice more or run a timed set.

Financial Management MCQ: The net cash flows of the project and their present values are as follows Year 1 2 3 4 Net cash flow (Rs) 5100 5100 5100 7100 PVIF @12% 0.893 0.797 0.712 0.636 Present Value (Rs) 4554 4065 3631 4516 The initial investment in the project is Rs12500, What is the NPV of the project? | Extra Education